SWORDv2 Project Plan – Timeline

This is the third in a series of blog posts outlining the SWORDv2 project plan.  This blog post details the proposed timeline of when each work package will take place.

The project is split into two phases, an initial research and specification phase, followed by a development and test phase.  During this time a second stream of advocacy and general community management will be undertaken.  There will also be a stream of work for project support.

Phase One: November 2010 – January 2011

  • Technical
    • Work package 1: Compile use cases
    • Work package 2: Analysis of white paper
    • Work package 4: Creation of prototype SWORD v2 specification
  • Community
    • Work package 3: Initial community formation
  • Project support
    • Work package 10: Project dissemination
    • Work package 11: Project administration

Phase Two: February 2011 – April 2011

  • Technical
    • Work package 5: Server implementations
    • Work package 6: Client implementations
  • Community
    • Work package 7: Instructional documentation and ongoing community management
    • Work package 9: Support the JISCDepo projects
  • Project support
    • Work package 8: Develop a sustainability plan
    • Work package 10: Project dissemination
    • Work package 11: Project administration